Latest activity by Tino Schaloske-
Tino Schaloske commented,
Official comment Hi Nicole, To compare planned and actual times, a detailed view is available for each production order. Do you need a cumulative view? Tino
-
Tino Schaloske commented,
Official comment Hi Nicole, Not yet; the manager can use filters in the order list, but not in the dashboard. We've developed a concept for this, but currently have several other important priorities. Tino
-
Tino Schaloske commented,
Official comment Hi Gus Ojeda, thanks for the request and sorry for the late response. I'd like to understand this in more detail. Currently, we mainly use manual inspection orders for exceptions, such as items tha...
-
Tino Schaloske commented,
Official comment Hi Greg, sorry for the late response. Here my feedback or questions: Why doesn't the operator report the end of their shift? For my understanding starting the wrong production order should be not t...
-
Tino Schaloske commented,
Official comment Hi Jeremy, Thank you for the feedback and sorry for the late answer. Your request could be absolutely useful and valuable for the standard. We've added it to our development log. Unfortunately, I c...
-
Tino Schaloske commented,
Official comment Hi Earl, This is definitely an issue that we have to face up to. In the first step, we had the idea of giving the auditor the opportunity to create another sample. Instead of closing the inspection...
-
Tino Schaloske commented,
Official comment Hi John, This is already planned. We are thinking about a general solution to give inspectors as well as operators in production access to inspection instructions or instructions for production. Ki...
-
Tino Schaloske commented,
Hi Chris, sorry for my late response. I will contact you for a meeting. Kind regards Tino
-
Tino Schaloske commented,
Official comment Hi Tim, This requirement makes absolute sense. As soon as we start working on flexible batch number definition and allocation, we will take this point into account. Kind regards Tino
-
Tino Schaloske commented,
Official comment Hi Matthew, with the option of defining production areas, there will also be a separate dashboard for each area. Kind regards Tino