It would be a very valuable and useful feature for me to allow creating color schemes in Just Plan It based on multiple criteria. For example, I would like to color tasks based on the following logic IF (Buffer Level = 0) AND (Shopfloor Status = Ready) THEN color as (Red).
Comments
4 comments
Hi Jeremy,
Thank you for the feedback and sorry for the late answer. Your request could be absolutely useful and valuable for the standard. We've added it to our development log. Unfortunately, I can't say yet when we'll be able to integrate it.
Tino
great idea.
Tino Schaloske Do you know yet if this is included in the next release?
Just curious, this feature seems like a pretty minor one and it is marked as planned for 10 months now. Is this still on the agenda?