Skip to main content

Automation for multiple inspection plans to be released on the same stage

Answered

Comments

5 comments

  • Official comment
    Tino Schaloske

    Hi Chris,

    I am not sure I understand the use case correctly. You have 3 operations and want to create a separate inspection plan/QC order for each operation, right? This case can be realized like this. It is important that the automation is clearly defined so that the same inspection plan is not used for each operation.

    Tino

  • Chris Cooney

    Hi Tino, no apologies we have 3 separate/ different inspection plans but want them to be triggered off 1 stage.  We can create the same automation for each inspection plan for 1 stage but only 1 inspection plan will be triggered automatically.

  • Tino Schaloske

    Hi Chris,

    i would like discuss this with you. Please send me you email address to schedule a call. Thanks,

    Tino

  • Chris Cooney

    Thanks - chris.cooney@vision33.co.uk

  • Tino Schaloske

    Hi Chris,

    sorry for my late response. I will contact you for a meeting.

    Kind regards Tino