Definition of "unhandled"
- Unhandled future processes, i.e., those that are to start after the scheduling start date. In case users have "played around" a lot and then may realize that they are no longer 100% satisfied with the plan, this feature helps them quickly replan starting from a certain date by moving the selected process to standby and then applying the "add all" function.
- Unhandled past processes, i.e., the routing status of which is not “in progress” or “finished”, meaning operations that should have started before the current work date but haven't.
Move unhandled operations to Standby per work or machine center
Sometimes planners don’t want to move the operations of the whole plan, but are focusing just on a single work or machine center and want a more granular version of this functionality.
The context menu of the work/machine center in the capacity view offers according options: