Q: How to set MRP didn't breakdown the subassembly from sales area
A: There is a parameter in MRP can determine breakdown the subassembly or not
The BOM structure like:
Assembly A
contain Sub-assembly B
contains Material C
If the switch is enabled, following requirement is displayed:
Assembly A
Assembly B
Material C
If the switch is disabled, following requirement is displayed:
Assembly A
Assembly B
In this case, Assembly B is no further broken down, Material C is not displayed as requirement.