The Resource View

  • Updated

The Resource View displays resource groups along with their respective resources, providing a clear visualization of capacity bottlenecks and scheduling conflicts.

Elements and symbols in the Resource View

Calendar

A calendar in the background of the Gantt chart shows weekends in grey, working times in white.

Absences of employees that are linked to resources are visualized in a light pink in the calendar and by a corresponding capacity curve.



Bars

Each job task is represented by a bar, the color of the job planning line bars depending on the job's category. The Job categories are indicated as follows:

 

 

A red frame indicates changes that have not been saved yet, and the orange frame highlights the currently marked task.

Sorting order

Within a resource group, resources are sorted in ascending alphabetical order.

Capacity curve

In the VJS, you can show a capacity curve in the Resource View to see free and exceeded capacities, a red box indicating an overload:

Creation mode

With the help of the creation mode, planners can interactively allocate a job task to a resource by dragging it from the list to the chart.

Find detailed information about the creation mode here.

 

 

 