To stay continuously informed about the progress of your operations, you can enable a progress bar beneath each production order routing line. You can choose whether the progress is calculated based on the quantity produced or the elapsed production time.
The color of the progress bar depends on the routing status and the percentage of completion. What’s more, finished operations get grayed out:
- Status “finished”:
- Status “none”, “planned”, “in progress”:
- Progress by quantity / by time < 100% : grey
-
- Progress by quantity / by time (i.e. you have posted more than initially planned) > 100%: red
When you have switched on "Automatic scheduling of predecessor" and/or "successor" the operation's routing status is being taken into account, so that if you want to move an operation that's in progress or whose predecessor/successor is in progress, you'll receive a warning message and can cancel or continue your action:
Comments
0 comments
Please sign in to leave a comment.