F9317-Operation sequence with parallel pool resource include APS Answered
We have pools of workers and pools of machines.
To get them started equal we like to use the parallel resources in the operation sequence.
So we need the function in the operation sequence and in the APS also.
We plan at least 70 new jobs a day with pools in the APS.
Comments
4 comments
Hi Christian
When you say "To get them started equal ", do you mean start the clock in of an operation and all parallel resources related at the same time ?
Hi Ana
yes we have pool of human resources and a pool of machines.
As machine needs human they must be available, planned and start at the same time.
Thanks to clarify
It was add it in our list of task to analyze in detail.
Best regards.