F9317-Operation sequence with parallel pool resource include APS Answered

Christian Hauff

We have pools of workers and pools of machines.

To get them started equal we like to use the parallel resources in the operation sequence.

So we need the function in the operation sequence and in the APS also.

We plan at least 70 new jobs a day with pools in the APS.

 

Comments

4 comments

  • Comment author
    Ana Bracho

    Hi Christian

    When you say "To get them started equal ", do you mean start the clock in of an operation and all parallel resources related at the same time ?

     

    0
  • Comment author
    Christian Hauff

    Hi Ana

    yes we have pool of human resources and a pool of machines.

    As machine needs human they must be available, planned and start at the same time.

    0
  • Comment author
    Ana Bracho

    Thanks to clarify

    It was add it in our list of task to analyze in detail.

    Best regards.

    0
  • Comment author
    Mounir AHANGUIR
    Hi Everyone,
    We have the same needs
    Is there a solution to that ?
     
    Regards,
    Mounir
    0