Add/remove work time

  • Updated

With the VAPS, you can comfortably define variations in capacity for multiple machine/work centers or entire shifts in one go

The VAPS lets you 

  • Add/remove work time for multiple machine/work centers in one interaction
  • Add/remove work time for entire shifts by work shift codes for one or multiple machine/work centers

Both options can be found under the "Actions" menu entry "Capacity Management"


In the picture below, downtimes have been added by date/time for two machine centers:

This is what the result looks like:

 

In the "Edit" dialog, you can change all your up/downtimes:

 

 