    Hi,

     (

       (  

         (Machine time + Labor time + Mach+labor time)

         if "per assembly" > 0 then

           (* (Order Quantity + Scrap) : (per assembly))

       : Utility factor

       * Work steps

         * (1 + scrap factor : 100)

       )

    + Set-up time

     )

    * Time factor (1 for minute, 60 for hours)

    * 100/Efficiency rate in %

    ==> One reason can be the Efficience rate defined in resource or scrap factor in folder extented

    https://help.beascloud.com/beas202109/index.html?berechnungdersollzeit.htm

     

  • Patrick Herr

    Hello Martin,

    thanks for the promt reply. I checked all factors in the formula (especially efficiency rate, scrap factor) and none of them explain the behaviour I observe. Like I said the funny thing is: after changing a random parameter in the routing position to a different value and then without confirming (Aktualisieren) the change of the routing position switching the parameter back to the initial value and the confirming leads to change of the reserved time (But actually no parameter of the routing position has been changed).

    Question: I changed in the routing position catalogue (Arbeitsgangkatalog), the master data (BEAS_APL) and in the work order (BEAS_FTAPL) the ressource allocation from percent to simple (Einfach). The entry in the field Mermaschinenbelegung_ANZ stays at the value 100 (as it was enterd for Percent) and cannot be changed. You think that this could have anything to do with the funny behaviour?

    Thanks in advance