Question regarding APS sheduling

Comments

2 comments

  • Martin Heigl

    Hi Patrik, 

    This is middle point calculation. Beas don't support this.
    The time critical resource must be the first resource to become this result.

    Alternative is option "latest as possible". But the result is related to delivery date and don't deliver exactly the result as you described.

     

    regards

    Martin

  • Patrick Herr

    Thank you very much. I will look into that. 

     

    Patrick