    Hi Daniel,

    in this example your opinion can be correct.

    But what is,if you work with scrap inside routing position or with different UoM

    Can be, that in fist operation you receipt 5 l and in second 10 pcs ( 0.5 l per l)
    Special in chemical industry the quantity can be different from one to another routing position

    regards

    Martin

     

    Comment actions Permalink
  • Avatar
    Daniel Gesk

    Hello Martin,

    thank you very much for your reply. I understand your position. In my case, the worker can´t start

    with routing 20. So I think it´s best to prepare a special template in the poollist.

    Best regards, Daniel