Shelf Life in months

Jose Manuel Costa

In some cases in recomendy that the expiration date was production date + shelf life (in months). 

We need to put the shelf life in months for the system (BEAS) works same as the printing machine. 

For example:

ítem A, with a shelf life 91 days (3 months)

Production day 31/08/2018

o  Expiration day for machine: 31/08/2018 + 3 months = 31/11/2018 CORRECT

o  Expiration day for BEAS: 31/08/2018 + 91 days = 30/11/2018 INCORRECT

 

ítem A, with a shelf life 92 days (3 months)

Production day 31/08/2018

o  Expiration day for machine: 31/08/2018 + 3 months = 31/11/2018 CORRECT

o  Expiration day for BEAS: 31/08/2018 + 92 days = 01/12/2018

     INCORRECT

 