Shift schedule for resources should be able END next day ( Example: Shift start 05:00 PM - Shift End 02:00AM )
Shift schedule for resources should be able END next day .
Example: Monday to Friday Shift start 05:00 PM - Shift End 02:00AM ( Capacity 9 hrs).
Beas is not able to considers this, so, the capacity is 0

The main problem in Dispatches APS
Start time and End time are not correctly.

Hope this can be considered in a close version.
Kind Regards
10
-
ademas no considera poder establecer los turnos por ejemplo que si un turno noche arrancan a las 22.00 del dia 01/04 y termina a las 06 AM 02/04 toda la produccion despues de las 24 deberia ser del 01/04