MRP considering all branches Answered

Fabio
I all,

Can I run an MRP by adding all the branches?
Example: I have all production in branch 1, but sales orders are in branch 2, 3, 4 and 5 I need to know how much I need to produce at branch 1 to serve all branches, considering the stock of each branch of course.

Rgs


Fabio

Comments

1 comment

  • Comment author
    Martin Heigl
    • Official comment

    It is possible to create one mrp for all branches

    But the system don't create sum of stock per branch. The system see only the stock from all defined warehouse

    You can calculate for all warehouse and in the recommendation list you can define, for which warehouse you want to see the inflow and outflow 

     

    see my Video
    youtube.com/watch?v=_8inKIBVxFQ&feature=emb_logo