Tool Change - APS Answered

Tugba

Hi,

One of our customers is using Tools in several operations. 

The question is : Is it possible to set a certain time for tool changing in APS? This certain time should be only active between the operations if the tool is different then the previous operation. If the tool is same as previous operation, it is not needed to calculate a change time.

Example:

Orders in APS:

Order 1 - Tool1

Order2  - Tool1

Order 3 - Tool2

Order 4 - Tool2

Order 5 - Tool3

So the tool change time should be calculated between 

Order 2 and Order 3

Order 4 and Order 5

 

Thanks

Comments

1 comment

  • Comment author
    Yaremi Miranda Lopez
    • Official comment

    Hello Tugba,

    This can be achieved with a Beas customization, please contact your local partner and if they need our assistance in the creation, they can contact us with this request.

    Best regards,

     

Please sign in to leave a comment.