Planning Capacity Resources in One Position Work Order and in the same Routing Position

Answered

Comments

1 comment

  • Daniel Gesk

    Hello Edwin,

    I recommend that you create not 10 resources but only 1 resource consisting of 10 machines/persons. In the routing position you can define how many of theses machines/persons should be considered for the calculation of the routing time.

    The following screenshots describe this possibility.

    Best regards, Daniel Gesk

     