9996 Maintenance Orders: Add new BOM or Routing lines
PlannedWhen working with corrective maintenance, the technical staff should be allowed to manually add new BOM or Routing lines, because they don't always know which part should be replaced when they are creating the Maintenance Orders. Even with preventive maintenance, it's possible to need to replace and unplanned component, and this is actually not possible.
Currently, the buttons "Bill of Materials Edit" and "Operation Sequence Edit" only works for editing the currently selected position, but doesn't allow to add or to remove lines.

Thanks,
Lucas.
-
Official comment
Hi Ethel,
Yes, now it is possible to click on the "New" button and select a new component for maintenance (both preventive/predictive and corrective). The same applies for the Routing.

Best regards,
Lucas.
-
Hi Lucas,
Is there an workarround in order to add materials or activities when we work with corrective maintenance?
Best regards,
Ethel
Please sign in to leave a comment.
Comments
2 comments