MRP for BOM & Production Orders - forecast by warehouse
AnsweredWould like the ability to be able to run the beas MRP by warehouse and have the Production Orders created with the user selected warehouse at run time using the demand on the forecast table.
Currently the Production Orders from the beas MRP get created with the warehouse defined on the BOM. I understand that the Warehouse UDF on the Forecast table is only used for filtering.
Our client has multiple warehouses and each can produce an BOMs so the production orders need to be created for the selected warehouse, not the warehouse set on the BOM.
0
-
Official commentDear Customer,
Certainly when we create a work order the warehouse define on the BOM is used by the system.
At this moment you can cover the scenario using versions or control version concept.
I would like understand better the scenario of your customer, why they need to produce by warehouse, are they using multi branches ? how many warehouse are involved ?Best regards,Ana Bracho