Saltar al contenido principal

Creating purchase request separately instead of integrating all requesting quantity into one single purchase request

Completada

Comentarios

5 comentarios

  • Alvaro Herrero

    Very interesting the feature that you are planning.

  • William Hsu[徐維廉]

    I appreciate that bro!

  • Ana Bracho

    Dear customer 

    We have to consider there is also customers that wants to consolidate the total quantity of the security date.

    You could consider use the option to order by week, this will apply for all items that has a quantity in that week, so it a simple steps it does not matter if just 3 Material or thousands. The system will transfer the quantity for all of items.

    Following your example you could create purchase for all items of week 50, then repeat for week 51,

     

     

  • Alvaro Herrero

    Thanks Ana for the suggestion. It´s a good solution.

  • WuPingHsien

    Hi

     

    Ana's method can solve some problems.

    But what if the demand day is >CW?

    The lead time of some materials is quite long and expensive.

    Impossible to reserve inventory in advance.