Operation that should not spread over multiple days
A times, we have operations for example oven time of 6 hours, which need to be continuously. Assuming oven capacity is 8 hours per day, one operation need 6 hours, the second operation need 5 hours. in this case, first operation is scheduled on day 1, and the second operation can not use the remaining 2 hours in day 1, instead the second oven run should be scheduled in second day. Hope this feature can be implemented in future.
Thanks
Liping