Creation of a new cost scheme separating the cost of materials by the group
Hi all.
Currently all the material in the structure is added to the "material cost", can I separate this cost by group in the configuration of the scheme?
Example:
raw material $ 100,00
separate:
raw material (group 100) $70,00
intermediate material (group 101) $20,00
packing (group 102) $ 10,00
Rgs
Fabio.
Beas 2021.02
-
You can create own schema objects with script

now you can sum all material group positions (more see documentation (F1 in this window))
Material line art=50
Purchase item: st_ke='E'
Price is in matkst
Problem: if you work with for - next, this can be slowfollow idea:
this is a datawindow, which support expression (see appeon help pages)
in beas you can call expression,if you use decimal values
instance decimal lc_value
all formulas evualated in dw_1. Note: this is not working in batch calculation, because here we use "dw_2"
formula
lc_value=sum(if(art=50 and st_gruppe="HM" ,matkst,0))
and then you can return the result
setvar=fccost=<cost,#0.00>
Note: don't forget the correct conversion with "#0.00"
complete script is
decimal cost
cost=sum(if(art=50 and st_gruppe="HM" and st_ke="K" ,matkst,0))
setvar=fccost=<cost,#0.00>
setvar=mccost=<cost,#0.00>
setvar=description=Material Group HM: <cost,#0.00>Note:
Not all rules included. No quarantee that it's working in every environment. Not working in batch calculation or post calculation
-
Good morning, I tried to filter my group but it doesn't work, the type filter works.
I left it on the filter until the group field alone to test but nothing unfortunately.Test1 - failed
decimal cost
cost=sum(if(st_gruppe="102" ,matkst,0))
setvar=fccost=<cost,#0.0000>
setvar=mccost=<cost,#0.0000>
setvar=description=Material Intermediário: <cost,#0.0000>Test 2 - failed
decimal cost
cost=sum(if(art=50 and st_gruppe="102" and st_ke="K" ,matkst,0))
setvar=fccost=<cost,#0.00>
setvar=mccost=<cost,#0.00>
setvar=description=Material Intermediário: <cost,#0.00>Test 3 - Pass
decimal cost
cost=sum(if(art=50 and st_ke="E" ,matkst,0))
setvar=fccost=<cost,#0.0000>
setvar=mccost=<cost,#0.0000>
setvar=description=Material Intermediário: <cost,#0.0000>In F1 there is no explanation of these variables that were used in the example.
Regards
Fabio.
-
Hi Fabio, i know. This solution is only a trick and is not working in every environment or batch calculation. This is the reason that we didn't described it
But if you can live with this limitations, then it's a fast good solution
Note
st_ke="E" = you make a sum of all assemblies
st_ke="K" = purchage items